My wife and I are building a modern modular home [by Method Homes] on Orcas Island. Watch the progress and see the construction complete by the end of 2010 (January 2011) (February 2011).
Links to Inspirations and Collaborators
Thursday, December 23, 2010
Appliances Rolling Down the Hill
Wednesday, December 22, 2010
Driveway, Tanks, Septic, and Cross-braces

Visitors
Saturday, December 4, 2010
Interior Progress
Exterior Progress
Method has made some significant progress on the outside of the house in the last week. The Insulation was corrected in the floors and the Hardieboard is installed under the house and on the mechanical room. We did have a few glitches with the Rain Catchment system and lost some water, but Ken Blair from Rainbank is rectifying the situation and will replace the lost water. Ken's pride in his work and integrity is really shining through. We appreciate it.Tuesday, November 30, 2010
Who'll Catch the Rain?
Siding, Mechanical Room, and Interior
Sunday, November 7, 2010
Progress
Saturday, October 23, 2010
Ready, Set, Set
Module Transport
Anne and I met the module in Anacortes for the 7:40 am ferry on 22-Oct. The transport team arrived around 7:00 for their reserved spot on the ferry. Everything went as planned an I was able to get some good pictures of the transportation team in motion. See the new transport slide show to left for more pictures.
Thursday, October 21, 2010
Staging the Spline
Monday, October 18, 2010
I kind of Miss the Orange
Monday, October 11, 2010
Weekly Update: Q&A
Mark Rylant: We are well into interior finishes with your cabinets installed (looking spectacular), tile half-way done (also looking great) hemlock t & g pre-stained and ready for install this week and final paint complete (minus touch up) also complete. On the exterior the siding is complete up to where we want it and should be getting preliminary paint coat this week. I’m happy with where we are at with the modules in the shop at this point. We’ll work as hard as possible over the next couple of weeks in order to ensure we have done all that we wanted to do prior delivery.
Patrick: Do we have a schedule for remaining work on the site?
- excavation?
Mark Rylant: The excavation is beginning again today. We are planning on back filling the main lower area with rock and gravel in order to install the slab for mechanical room later this week including the final layer of rock for the water tanks, which I want to wait on install so that we have a dry area during site finishing to work and stage material. One good point Ken Blair made was to install the tanks asap so that we may begin collecting October rain. We discussed installing at least one or two of the tanks so that the collection may begin.
So we should be working on excavation for a few days this week. This will get us ready for crane and modular delivery. Then, there will be one final return from Orcas Excavation for site clean up, shaping the drive/parking and final grading. At this time they may or may not be able to install septic...if not soon there after.
Patrick: - foundation?
Mark Rylant; The foundation is complete at this point with only the small mechanical slab needed to be completed. So that will hopefully happen this week. I am taking final measurements for steel fabrication today, which will be done by the end of this week, with steel and wood framing to begin on Monday the 18th...which should take a few days and be ready just before set.
Patrick: Are we still on target for 22-Oct? Mark Rylant: Yes.
Patrick: - what's the schedule for module transport?
Mark Rylant: I believe one module will be leaving as early as the 20th.
Patrick: - at what point will our neighbors be inconvenienced?
Mark Rylant: I’ve met most of the neighbors and from here on out they should only be inconvenienced on the day of set, minus a delivery truck of material here and there. Let me know if you have any ideas on that and the trimming of the trees up and down the drive that will need to be dealt with.
Sunday, October 3, 2010
Factory Update
Ready, Set, Pour
Tuesday, September 28, 2010
Factory
Foundation
Thursday, September 9, 2010
Factory Work Is Humming Right Along
Ready, Set, Dig
Tuesday, August 24, 2010
Let the Building Begin
Sunday, August 8, 2010
Interior Finishes Chosen
We met with the cabinetmaker, Wes from Smith and Vallee http://www.smithandvallee.com this weekend. Smith and Vallee will provide the kitchen cabinets, desk spaces, and media cabinet. We have also chosen the appliances so that the cabinets can be custom fit.
We have made the final decisions on interior finishes. The picture shows the materials which includes black walnut veneer (cabinets, desk area, and vanities), hemlock vertical grain (ceiling and sils), Teragren Synergy strand bamboo flooring http://www.teragren.com/, Polar White Eco by Constentino (counter tops) http://www.ecobycosentino.com/, Fondavalle Pietra Dura 18x18 tile, and black river stone accents http://www.vasqueztile.com/.
Saturday, July 17, 2010
Architecture and Design (2010)
Anne is an energy efficiency specialist (and a designer and a physicist and a engineer) and I am an engineer (and a photographer and a writer). So, needless to say, we have some creative bones in our bodies. We tried our best to make sure everyone knew that we wanted collaboration throughout the design phase.In the February and March timeframe we had a few visits with the architects and builders, including one on-site meeting. At this time we made the final decision to separate the modules, and shortly after I suggested a simplified connector that we came to loving call the “spine”.
The design at the top of this blog entry is credited to balance associates architects. If you’ve looked at Method’s website, you’ll note that we ventured pretty far away from the standard cabin 3. The front and back module, along with the roof, will be build in the factory, while the spine will be site-built. So, while we are doing some site building and we got to permitting later that expected 21-Jun-2010, we are still targeting a move in date of 15-Dec-2010. This is predicated on receiving the go-ahead from the county permitting folks by mid-August. Still, that’s impressive.
Water availability was also interesting for this project. When we purchased the property we were “promised” water rights – in writing. The quote from 2006 was that water would be available in three to six months. Funny part is that when we asked for a water availability certificate in 2010, we got the same answer. Luckily, I had made the executive decision to get a water catchment design from Ken Blair at Rain Bank. He’s the foremost authority on catchment on the San Juan Islands. He had the paper work ready in two weeks and it was approved in ONE DAY. That was money well spent.
I had modeled the worst 3 year period of rainfall over the past 125 years and determined that based on our water usage we would need 12,000 gallons of water storage to get us through the summer months of the worst drought years on record. All of our appliances will be super water and energy efficient, and we’ve incorporated other water saving ideas in the home: circulating water back the water heater until it gets hot, instead of letting it flow down the drain. The four three-thousand gallon tanks will fit under the forward module with very little excavation. The water from the roof will be filtered for large particulate before it goes in the eves. Then further filtering occurs before the tanks. Once, the water comes out of the tanks it goes through two more particulate filters and a UV filter. This will be far cleaner than any water from a utility.
Feasibility (2009)
Turns out it was feasible and not all that expensive for the transportation.
Builder Choice (2009)
After a little more research, Anne found Method Homes (http://www.methodhomes.net/). One key difference is that the owners of this company are builders. That practical aspect was key to our decision. The design itself was created by balance associated architects (http://www.balanceassociates.com/). They are known for their open and sustainable designs.
Anne and I chose the Method’s Cabin 3 design as the starting point. With the finish choices, we’re confident we can create the home we want. As it turns out, our lot isn’t suited for a standard Cabin 3. So, we made changes in collaboration with the builder and architects while preserving the 2 main modules.
Why Modular (2008)
In modular construction, much of the building is done in controlled environments in a factory. Not only is the building protected from the elements, but work is easier because jigs are used to ensure level and square construction. It’s also remarkable how quickly the modules can be built in a factory.
The modular style we chose creates sections of the home and installs sheet rock, cabinets, windows, some floors, and some siding in the factory. The bonus is that the home is built stronger in order to sustain travel.
To this day, I still believe that it will also be cheaper to build a modular home due to the timeframe of the build and process for the decisions.
The Search for Land (Apr-2006)
Despite the relatively small size of the island, there is quite a range of quality in the land that is available for purchase. First, location is key for several reasons: water availability and rain fall varies wildly, building restrictions are sometimes too tight and sometimes too loose, and distance from the ferry landing (this may seem odd on an island, but the highest speed limit is 40mph and it can take over an hour to reach some properties). So those lots we had researched were not desirable for one reason or another.
Needless to say, sticker shot set in. After two trips to Orcas to specifically look for land, we came up empty. Along the way we found a realtor we trusted (who's no longer on the island) and that turned out to be the key. A piece of property in the Rosario area ticked down in price. This was unheard of in 2006. So, the realtor gave us call, described the property to us, and we ended up buying the property sight unseen, with the contingency that we could back out after a site visit. It all worked out and we became the proud owners of Orcas Island property in April of 2006.
The land we purchased has a slope to it and that will come into play when we start to describe construction planning and site costs.
First Visit (2002)
We were immediately drawn to the island and people we met there. Beyond a basic sense of well being, we felt like we belonged.



